SOLAR Β· PJMSolar project AG2-684, Metcalfe County
Solar project AG2-684, Metcalfe County is a 331 MW solar request withdrawn in the PJM interconnection queue, in Metcalfe County, Kentucky, connecting to EKPC.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2021 (completed)
- Withdrawn / abandonedDec 2024 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AG2-684
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- EKPC
- Connection point (POI)
- Summer Shade 161 kV
- Location
- Metcalfe County, Kentucky
- Technology
- Solar: 331 MW
- Total requested
- 331 MW
- Service type
- Network resource (NRIS)
- Study phase
- Feasibility Study
- Queue status
- Withdrawn
- Entered queue
- 31 March 2021
- Proposed online date
- June 2024
- Withdrawn
- December 2024
Location
Marker shows the centre of Metcalfe County; the queue data does not give exact sites.
Other requests in Metcalfe County
- Summer Shade SolarSolar + storage Β· 106 MW Β· agreement signed
- Glover Creek SolarSolar Β· 35.0 MW Β· built
- Glover Creek SolarSolar Β· 20.0 MW Β· built
- Other project 132, Metcalfe CountyOther Β· 640 MW Β· withdrawn
- Other project 57, Metcalfe CountyOther Β· 640 MW Β· withdrawn
- Solar project AG2-094, Metcalfe CountySolar Β· 150 MW Β· withdrawn
- Solar project AH1-083, Metcalfe CountySolar Β· 100 MW Β· withdrawn
- Solar project AH1-081, Metcalfe CountySolar Β· 60.0 MW Β· withdrawn
- Solar + storage project AG2-598, Metcalfe CountySolar + storage Β· 50.0 MW Β· withdrawn
- Solar project AH1-082, Metcalfe CountySolar Β· 44.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem