United States › Grid › Interconnection queues › Kentucky
SOLAR · PJMSolar project AH1-664, Fleming County
Solar project AH1-664, Fleming County is a 100 MW solar request in interconnection study in the PJM interconnection queue, in Fleming County, Kentucky, connecting to EKPC.
Queue statusIn planning
- PlanningQueued Feb 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- Operating (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- AH1-664
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- EKPC
- Developer
- Hummingbird Energy LLC
- Connection point (POI)
- Goddard-Plumville 138 kV
- Location
- Fleming County, Kentucky
- Technology
- Solar: 100 MW
- Total requested
- 100 MW
- Service type
- Network resource (NRIS)
- Study phase
- System Impact Study
- Queue status
- Active
- Entered queue
- 21 February 2025
Location
Marker shows the centre of Fleming County; the queue data does not give exact sites.
Other requests in Fleming County
- Fleming SolarSolar · 189 MW · agreement signed
- Solar project AH1-666, Fleming CountySolar · 80.0 MW · in study
- Solar project AH1-665, Fleming CountySolar · 80.0 MW · in study
- Solar + storage project AH2-383, Fleming CountySolar + storage · 70.0 MW · in study
- Solar + storage project AI1-133, Fleming CountySolar + storage · 50.0 MW · in study
- Solar project LGE-GIS-2018-007, Fleming CountySolar · 120 MW · withdrawn
- Solar project AH1-429, Fleming CountySolar · 90.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem