United States › Grid › Interconnection queues › Kentucky
SOLAR · SOUTHEASTSolar project LGE-CS2025-013, Ballard County
Solar project LGE-CS2025-013, Ballard County is a 100 MW solar request in interconnection study in the Southeast interconnection queue, in Ballard County, Kentucky, connecting to Louisville Gas & Electric and Kentucky Utilities Energy.
- PlanningQueued Dec 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jun 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- LGE-CS2025-013
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Louisville Gas & Electric and Kentucky Utilities Energy
- Connection point (POI)
- Grahamville - Wickliffe 161kV line tap
- Location
- Ballard County, Kentucky
- Technology
- Solar: 100 MW
- Total requested
- 100 MW
- Service type
- NRIS and ERIS
- Study phase
- In Progress (unknown study)
- Queue status
- Active
- Entered queue
- 24 December 2025
- Proposed online date
- June 2028
Location
Marker shows the centre of Ballard County; the queue data does not give exact sites.
Other requests in Ballard County
- Solar project LGE-GIS-2022-001, Ballard CountySolar · 125 MW · withdrawn
- Solar project LGE-GIS-2019-002, Ballard CountySolar · 104 MW · withdrawn
- Solar project LGE-GIS-2019-014, Ballard CountySolar · 100 MW · withdrawn
- Solar project LGE-GIS-2019-021, Ballard CountySolar · 80.0 MW · withdrawn
- Other project G508, Ballard CountyOther · 15.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem