United States β€Ί Grid β€Ί Interconnection queues β€Ί Kentucky

SOLAR Β· SOUTHEAST

Solar project LGE-GIS-2019-021, Ballard County

Solar project LGE-GIS-2019-021, Ballard County is a 80.0 MW solar request withdrawn in the Southeast interconnection queue, in Ballard County, Kentucky, connecting to Louisville Gas & Electric and Kentucky Utilities Energy.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2019 (completed)
  2. Withdrawn / abandonedJun 2019 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
LGE-GIS-2019-021
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Louisville Gas & Electric and Kentucky Utilities Energy
Connection point (POI)
Barlow - Forrestdale 69 kV line
Location
Ballard County, Kentucky
Technology
Solar: 80.0 MW
Total requested
80.0 MW
Service type
NRIS and ERIS
Queue status
Withdrawn
Entered queue
27 March 2019
Proposed online date
January 2022
Withdrawn
June 2019

Location

Marker shows the centre of Ballard County; the queue data does not give exact sites.

Power plants in Kentucky Β· Transmission lines in Kentucky

Other requests in Ballard County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem