United States › Grid › Interconnection queues › Kentucky

BATTERY STORAGE · PJM

Threeforks Energy Storage

Threeforks Energy Storage is a 100 MW battery storage request with a signed interconnection agreement in the PJM interconnection queue, in Martin County, Kentucky, connecting to AEP.

Queue statusConsented
  1. PlanningQueued Sep 2019 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget May 2028 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
AF1-162
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Connection point (POI)
Inez 138 kV
Location
Martin County, Kentucky
Technology
Battery: 100 MW
Total requested
100 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Active
Entered queue
20 September 2019
Proposed online date
May 2028

Location

Marker shows the centre of Martin County; the queue data does not give exact sites.

Power plants in Kentucky · Transmission lines in Kentucky