Martin County Solar Project

Martin County Solar Project is a 190 MW solar request suspended in the PJM interconnection queue, in Martin County, Kentucky, connecting to AEP.

Queue statusPaused / redesign
  1. PlanningQueued Sep 2019 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
AF1-130
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Connection point (POI)
Inez 138 kV
Location
Martin County, Kentucky
Technology
Solar: 190 MW
Total requested
190 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Suspended
Entered queue
20 September 2019
Proposed online date
December 2028

Location

Marker shows the centre of Martin County; the queue data does not give exact sites.

Power plants in Kentucky · Transmission lines in Kentucky

Other requests in Martin County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem