United States › Grid › Interconnection queues › Kentucky

SOLAR · PJM

Lynn Bark Energy Center

Lynn Bark Energy Center is a 200 MW solar request with a signed interconnection agreement in the PJM interconnection queue, in Martin County, Kentucky, connecting to AEP.

Queue statusConsented
  1. PlanningQueued Nov 2019 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Mar 2029 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
AF2-018
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Connection point (POI)
Inez 138 kV
Location
Martin County, Kentucky
Technology
Solar: 200 MW
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Active
Entered queue
1 November 2019
Proposed online date
March 2029

Location

Marker shows the centre of Martin County; the queue data does not give exact sites.

Power plants in Kentucky · Transmission lines in Kentucky

Other requests in Martin County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem