Solar + storage project AI1-019

Solar + storage project AI1-019 is a 50.0 MW solar + storage request in interconnection study in the PJM interconnection queue, connecting to EKPC.

Queue statusIn planning
  1. PlanningQueued Apr 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2026 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
AI1-019
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
EKPC
Connection point (POI)
Laurel - Cooper 161 kV
Location
Kentucky
Technology
Solar: 50.0 MW · Battery
Total requested
50.0 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Active
Entered queue
1 April 2022
Proposed online date
December 2026

Location

No county location in the queue data.