🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Kentucky

SOLAR · PJM

Solar project AG2-073, Madison County

Solar project AG2-073, Madison County is a 53.0 MW solar request in interconnection study in the PJM interconnection queue, in Madison County, Kentucky, connecting to EKPC.

Queue statusIn planning
  1. PlanningQueued Mar 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget May 2024 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
AG2-073
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
EKPC
Developer
SR Madison, LLC
Connection point (POI)
Crooksville 69 kV
Location
Madison County, Kentucky
Technology
Solar: 53.0 MW
Total requested
53.0 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Active
Entered queue
4 March 2025
Proposed online date
May 2024

Location

Marker shows the centre of Madison County; the queue data does not give exact sites.

Power plants in Kentucky · Transmission lines in Kentucky

Other requests in Madison County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem