SOLAR Β· PJMSolar project AF1-267, Madison County
Solar project AF1-267, Madison County is a 54.0 MW solar request withdrawn in the PJM interconnection queue, in Madison County, Kentucky, connecting to EKPC.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2019 (completed)
- Withdrawn / abandonedNov 2020 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AF1-267
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- EKPC
- Connection point (POI)
- Union City Tap 138 kV
- Location
- Madison County, Kentucky
- Technology
- Solar: 54.0 MW
- Total requested
- 54.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study
- Queue status
- Withdrawn
- Entered queue
- 30 September 2019
- Proposed online date
- January 2022
- Withdrawn
- November 2020
Location
Marker shows the centre of Madison County; the queue data does not give exact sites.
Other requests in Madison County
- Madison Solar 1Solar Β· 100 MW Β· in study
- Solar project AG2-073, Madison CountySolar Β· 53.0 MW Β· in study
- Solar project AF2-348, Madison CountySolar Β· 250 MW Β· withdrawn
- Solar project AF2-355, Madison CountySolar Β· 225 MW Β· withdrawn
- Solar project AI1-084, Madison CountySolar Β· 150 MW Β· withdrawn
- Solar project AE2-275, Madison CountySolar Β· 90.0 MW Β· withdrawn
- Solar project AH1-410, Madison CountySolar Β· 68.0 MW Β· withdrawn
- Solar project AG1-306, Madison CountySolar Β· 65.0 MW Β· withdrawn
- Solar project LGE-GIS-2020-001, Madison CountySolar Β· 50.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem