United States › Grid › Interconnection queues › Kentucky
SOLAR · PJMBright Mountain Solar
Bright Mountain Solar is a 80.0 MW solar request with a signed interconnection agreement in the PJM interconnection queue, in Perry County, Kentucky, connecting to AEP.
Queue statusConsented
- PlanningQueued Jul 2020 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Jan 2027 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- AG1-066
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- AEP
- Connection point (POI)
- Bonnyman 69 kV
- Location
- Perry County, Kentucky
- Technology
- Solar: 80.0 MW
- Total requested
- 80.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
- Queue status
- Active
- Entered queue
- 30 July 2020
- Proposed online date
- January 2027
Location
Marker shows the centre of Perry County; the queue data does not give exact sites.
Other requests in Perry County
- Solar + storage project AH2-076, Perry CountySolar + storage · 52.5 MW · in study
- Coal project O69, Perry CountyCoal · 535 MW · withdrawn
- Solar project AG2-681, Perry CountySolar · 150 MW · withdrawn
- Solar project AD2-106, Perry CountySolar · 80.0 MW · withdrawn
- Other project Y2-086, Perry CountyOther · 62.5 MW · withdrawn
- Other project W4-039, Perry CountyOther · 62.5 MW · withdrawn
- Solar project AD2-107, Perry CountySolar · 55.0 MW · withdrawn
- Other project V3-055, Perry CountyOther · 50.0 MW · withdrawn
- Battery storage project AE2-208, Perry CountyBattery storage · 25.0 MW · withdrawn
- Other project W2-062, Perry CountyOther · 12.1 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem