OTHER Β· PJMOther project V3-055, Perry County
Other project V3-055, Perry County is a 50.0 MW other request withdrawn in the PJM interconnection queue, in Perry County, Kentucky, connecting to AEP.
Queue statusWithdrawn / abandoned
- PlanningQueued Oct 2009 (completed)
- Withdrawn / abandonedAug 2010 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- V3-055
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- AEP
- Connection point (POI)
- Engle 69kV
- Location
- Perry County, Kentucky
- Technology
- Other: 50.0 MW
- Total requested
- 50.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Withdrawn
- Queue status
- Withdrawn
- Entered queue
- 23 October 2009
- Proposed online date
- January 2013
- Withdrawn
- August 2010
Location
Marker shows the centre of Perry County; the queue data does not give exact sites.
Other requests in Perry County
- Bright Mountain SolarSolar Β· 80.0 MW Β· agreement signed
- Solar + storage project AH2-076, Perry CountySolar + storage Β· 52.5 MW Β· in study
- Coal project O69, Perry CountyCoal Β· 535 MW Β· withdrawn
- Solar project AG2-681, Perry CountySolar Β· 150 MW Β· withdrawn
- Solar project AD2-106, Perry CountySolar Β· 80.0 MW Β· withdrawn
- Other project Y2-086, Perry CountyOther Β· 62.5 MW Β· withdrawn
- Other project W4-039, Perry CountyOther Β· 62.5 MW Β· withdrawn
- Solar project AD2-107, Perry CountySolar Β· 55.0 MW Β· withdrawn
- Battery storage project AE2-208, Perry CountyBattery storage Β· 25.0 MW Β· withdrawn
- Other project W2-062, Perry CountyOther Β· 12.1 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem