Solar + storage project AH2-076, Perry County

Solar + storage project AH2-076, Perry County is a 52.5 MW solar + storage request in interconnection study in the PJM interconnection queue, in Perry County, Kentucky, connecting to AEP.

Queue statusIn planning
  1. PlanningQueued Jan 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2023 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
AH2-076
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Connection point (POI)
Bonneyman - Softshell 138 kV
Location
Perry County, Kentucky
Technology
Solar: 52.5 MW · Battery
Total requested
52.5 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Active
Entered queue
26 January 2022
Proposed online date
December 2023

Location

Marker shows the centre of Perry County; the queue data does not give exact sites.

Power plants in Kentucky · Transmission lines in Kentucky

Other requests in Perry County