πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Kentucky

SOLAR Β· PJM

Barrelhead

Barrelhead is a 54.0 MW solar request with a signed interconnection agreement in the PJM interconnection queue, connecting to EKPC.

Queue statusConsented
  1. PlanningQueued Sep 2020 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Jan 2029 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
AG1-471
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
EKPC
Developer
Barrelhead Solar, LLC
Connection point (POI)
Up Church-Wayne County 69 kV
Location
Kentucky
Technology
Solar: 54.0 MW
Total requested
54.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Document Posted
Queue status
Active
Entered queue
30 September 2020
Proposed online date
January 2029

Location

No county location in the queue data.

Power plants in Kentucky Β· Transmission lines in Kentucky

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem