United States β€Ί Grid β€Ί Interconnection queues β€Ί Kentucky

SOLAR Β· PJM

Pike County Solar

Pike County Solar is a 50.0 MW solar request suspended in the PJM interconnection queue, in Pike County, Kentucky, connecting to AEP.

Queue statusPaused / redesign
  1. PlanningQueued Oct 2016 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
AC1-102
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Connection point (POI)
Johns Creek-Excel 138kV II
Location
Pike County, Kentucky
Technology
Solar: 50.0 MW
Total requested
50.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Suspended
Entered queue
25 October 2016
Proposed online date
December 2028

Location

Marker shows the centre of Pike County; the queue data does not give exact sites.

Power plants in Kentucky Β· Transmission lines in Kentucky

Other requests in Pike County