United States βΊ Grid βΊ Interconnection queues βΊ Kentucky
ONSHORE WIND Β· PJMOnshore wind project W3-051, Pike County
Onshore wind project W3-051, Pike County is a 60.0 MW onshore wind request withdrawn in the PJM interconnection queue, in Pike County, Kentucky, connecting to AEP.
Queue statusWithdrawn / abandoned
- PlanningQueued Aug 2010 (completed)
- Withdrawn / abandonedJan 2012 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- W3-051
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- AEP
- Connection point (POI)
- Dorton 138kV
- Location
- Pike County, Kentucky
- Technology
- Wind: 60.0 MW
- Total requested
- 60.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study
- Queue status
- Withdrawn
- Entered queue
- 31 August 2010
- Proposed online date
- September 2013
- Withdrawn
- January 2012
Location
Marker shows the centre of Pike County; the queue data does not give exact sites.
Other requests in Pike County
- Solar project AI2-333, Pike CountySolar Β· 40.0 MW Β· in study
- Solar project AH2-117, Pike CountySolar Β· 30.0 MW Β· in study
- Solar project AI2-342, Pike CountySolar Β· 15.4 MW Β· in study
- Pike County SolarSolar Β· 50.0 MW Β· suspended
- Pike County SolarSolar Β· 50.0 MW Β· suspended
- Solar project AF2-328, Pike CountySolar Β· 75.0 MW Β· withdrawn
- Solar + storage project AH1-418, Pike CountySolar + storage Β· 50.0 MW Β· withdrawn
- Solar + storage project AH2-276, Pike CountySolar + storage Β· 40.0 MW Β· withdrawn
- Solar project AF2-017, Pike CountySolar Β· 20.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem