United States › Grid › Interconnection queues › Kentucky
SOLAR · PJMSolar project AI2-342, Pike County
Solar project AI2-342, Pike County is a 15.4 MW solar request in interconnection study in the PJM interconnection queue, in Pike County, Kentucky, connecting to AEP.
Queue statusIn planning
- PlanningQueued Mar 2023 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Mar 2027 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- AI2-342
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- AEP
- Connection point (POI)
- Excel-Johns Creek 138 kV
- Location
- Pike County, Kentucky
- Technology
- Solar: 15.4 MW
- Total requested
- 15.4 MW
- Service type
- Network resource (NRIS)
- Study phase
- Feasibility Study
- Queue status
- Active
- Entered queue
- 2 March 2023
- Proposed online date
- March 2027
Location
Marker shows the centre of Pike County; the queue data does not give exact sites.
Other requests in Pike County
- Solar project AI2-333, Pike CountySolar · 40.0 MW · in study
- Solar project AH2-117, Pike CountySolar · 30.0 MW · in study
- Pike County SolarSolar · 50.0 MW · suspended
- Pike County SolarSolar · 50.0 MW · suspended
- Solar project AF2-328, Pike CountySolar · 75.0 MW · withdrawn
- Onshore wind project W3-051, Pike CountyOnshore wind · 60.0 MW · withdrawn
- Solar + storage project AH1-418, Pike CountySolar + storage · 50.0 MW · withdrawn
- Solar + storage project AH2-276, Pike CountySolar + storage · 40.0 MW · withdrawn
- Solar project AF2-017, Pike CountySolar · 20.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem