United States β€Ί Grid β€Ί Interconnection queues β€Ί Kentucky

SOLAR + STORAGE Β· PJM

Solar + storage project AH2-276, Pike County

Solar + storage project AH2-276, Pike County is a 40.0 MW solar + storage request withdrawn in the PJM interconnection queue, in Pike County, Kentucky, connecting to AEP.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2022 (completed)
  2. Withdrawn / abandonedOct 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AH2-276
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Connection point (POI)
Second Fork 69 kV
Location
Pike County, Kentucky
Technology
Solar: 40.0 MW Β· Battery
Total requested
40.0 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
10 March 2022
Proposed online date
March 2024
Withdrawn
October 2025

Location

Marker shows the centre of Pike County; the queue data does not give exact sites.

Power plants in Kentucky Β· Transmission lines in Kentucky

Other requests in Pike County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem