Interconnection queue in Indiana — page 5

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown30059.6 GW
Active in queue59.6 GW300 requests
Agreement signed11.2 GW69 requests
Withdrawn579114.4 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

300 requests · page 5 of 6
ProjectCapacityStatusLocationRegionQueuedOnline
Flatrock Creek Solar II
Solar
100 MWAgreement signed Allen, INPJM Sep 2020target 2029
Headwaters Wind Farm III
Onshore wind
100 MWPaused / redesign Randolph, INPJM Sep 2018target 2026
Madison County Solar
Solar
100 MWPaused / redesign Madison, INPJM Mar 2018target 2025
Battery storage project AG2-343, Fountain County
Battery storage · Dolphin Solar LLC
100 MWIn study Fountain, INPJM Feb 2025target 2024
Onshore wind project J2440, Benton County
Onshore wind
100 MWIn study Benton, INMISO Sep 2022target 2027
Solar project J1407, Porter County
Solar
100 MWAgreement signed Porter, INMISO Apr 2019target 2025
Prairie Creek Wind Phase 2
Onshore wind · Prairie Creek Wind Farm II, LLC
100 MWAgreement signed Blackford, INPJM Sep 2020target 2029
Flatrock Creek Solar I
Solar
100 MWAgreement signed Allen, INPJM Mar 2020target 2029
Solar project AG2-550, Randolph County
Solar · Riverstart Solar Park VI LLC
100 MWIn study Randolph, INPJM Feb 2025target 2024
Battery storage project J2232, Tipton County
Battery storage
100 MWIn study Tipton, INMISO Aug 2021target 2024
Solar project J1391, Dubois County
Solar
100 MWAgreement signed Dubois, INMISO Apr 2019target 2025
Headwaters Wind Farm III
Onshore wind
100 MWPaused / redesign Randolph, INPJM Sep 2018target 2026
Solar + storage project AI1-081, Jay County
Solar + storage
100 MWIn study Jay, INPJM Jul 2022target 2026
Battery storage project J3166, Knox County
Battery storage
100 MWIn study Knox, INMISO Sep 2022target 2026
Battery storage project J2450, Tippecanoe County
Battery storage
100 MWIn study Tippecanoe, INMISO Sep 2022target 2026
Tillman Solar Park
Solar
100 MWAgreement signed Allen, INPJM Sep 2020target 2029
Battery storage project AH2-233, Pulaski County
Battery storage
100 MWIn study Pulaski, INPJM Mar 2022target 2026
Riverstart Solar Park V
Solar
100 MWPaused / redesign Randolph, INPJM Mar 2019target 2026
Battery storage project AG2-248, Elkhart County
Battery storage · Amberjack Solar LLC
100 MWIn study Elkhart, INPJM Jan 2025target 2024
Solar project J1785, Laporte County
Solar
100 MWIn study Laporte, INMISO Jan 2022target 2024
Solar + storage project J2301, Vigo County
Solar + storage
100 MWIn study Vigo, INMISO Mar 2022target 2025
Solar + storage project AI1-009, Rush County
Solar + storage
100 MWIn study Rush, INPJM Apr 2022target 2026
Replacing 100 MW of Solar with storage; J1386
Battery storage
100 MWIn study Lake, INMISO Jul 2025target 2028
Solar project J903, Henry County
Solar
100 MWUnder construction Henry, INMISO Jun 2017target 2023
Sun Chief Solar Farm
Solar
100 MWAgreement signed Jay, INPJM Jul 2020target 2027
Solar project J2296, Sullivan County
Solar
100 MWIn study Sullivan, INMISO Mar 2022target 2025
Solar project J1369, Dubois County
Solar
100 MWAgreement signed Dubois, INMISO Apr 2019target 2025
Solar project J1392, Lagrange County
Solar
100 MWAgreement signed Lagrange, INMISO Apr 2019target 2025
Solar project J1736, Dubois County
Solar
100 MWIn study Dubois, INMISO Jun 2020target 2023
Onshore wind project J2048, Benton County
Onshore wind
100 MWIn study Benton, INMISO Mar 2022target 2025
Surplus; J1190
Battery storage
100 MWIn study Lagrange, INMISO Jul 2025target 2027
Solar project AH1-392, St. Joseph County
Solar · ibV Energy Partners LLC
90.0 MWIn study St. Joseph, INPJM Feb 2025target 2025
Solar project J847, Jasper County
Solar
90.0 MWUnder construction Jasper, INMISO Jun 20172023
Gas project J3870, Vigo County
Gas
87.0 MWIn study Vigo, INMISO Dec 2024target 2002
Solar project AI2-115, Delaware County
Solar
84.0 MWIn study Delaware, INPJM Feb 2023target 2026
Hawthorn Solar
Solar
83.0 MWAgreement signed Delaware, INPJM Sep 2019target 2028
Fall Creek Energy Storage
Battery storage
80.0 MWAgreement signed Madison, INPJM Mar 2020target 2028
Battery storage project AH1-482, Pulaski County
Battery storage · Lightsource Renewable Energy Development, LLC
78.0 MWIn study Pulaski, INPJM Feb 2025target 2023
Battery storage project AH2-227, Jay County
Battery storage
75.0 MWIn study Jay, INPJM Mar 2022target 2026
Battery storage project AH1-302, Pulaski County
Battery storage · Bottlebrush Solar Energy LLC
75.0 MWIn study Pulaski, INPJM Feb 2025target 2025
BR Solar Sheriff 1
Solar
75.0 MWAgreement signed Grant, INPJM Sep 2020target 2028
Solar project J3896, Knox County
Solar
70.0 MWIn study Knox, INMISO Feb 2025target 2030
Solar project J4034, Vigo County
Solar
70.0 MWIn study Vigo, INMISO Jun 2025target 2030
Solar project J3925, Knox County
Solar
70.0 MWIn study Knox, INMISO Feb 2025target 2030
Solar project J783, Spencer County
Solar
70.0 MWUnder construction Spencer, INMISO Nov 2016target 2021
Solar project J2177, Tipton County
Solar
67.0 MWIn study Tipton, INMISO Aug 2021target 2024
Solar + storage project AG2-519, Delaware County
Solar + storage · Muncie Solar 1, LLC
66.5 MWIn study Delaware, INPJM Mar 2025target 2024
Surplus; J1067
Other
60.0 MWIn study White, INMISO May 20222024
Solar project J1387, Jasper County
Solar
60.0 MWAgreement signed Jasper, INMISO Apr 2019target 2024
Solar project J3897, Knox County
Solar
60.0 MWIn study Knox, INMISO Feb 2025target 2030

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)