SOLAR · PJMBR Solar Sheriff 1
BR Solar Sheriff 1 is a 75.0 MW solar request with a signed interconnection agreement in the PJM interconnection queue, in Grant County, Indiana, connecting to AEP.
Queue statusConsented
- PlanningQueued Sep 2020 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Apr 2028 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- AG1-414
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- AEP
- Connection point (POI)
- Mississinewa 138 kV
- Location
- Grant County, Indiana
- Technology
- Solar: 75.0 MW
- Total requested
- 75.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
- Queue status
- Active
- Entered queue
- 30 September 2020
- Proposed online date
- April 2028
Location
Marker shows the centre of Grant County; the queue data does not give exact sites.
Other requests in Grant County
- Solar + storage project AI1-134, Grant CountySolar + storage · 200 MW · in study
- Solar + storage project AG2-191, Grant CountySolar + storage · 30.0 MW · in study
- Solar + storage project AG2-192, Grant CountySolar + storage · 19.0 MW · in study
- Golden Aster Solar Energy CenterSolar · 160 MW · suspended
- Golden Aster Solar Energy CenterBattery storage · 40.0 MW · suspended
- Deer Creek Solar FacilitySolar · 2.5 MW · built
- Solar project J2251, Grant CountySolar · 200 MW · withdrawn
- Solar + storage project AF2-204, Grant CountySolar + storage · 110 MW · withdrawn
- Solar + storage project AG2-412, Grant CountySolar + storage · 100 MW · withdrawn
- Solar + storage project AG2-546, Grant CountySolar + storage · 40.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem