United States › Grid › Interconnection queues › Indiana
SOLAR · PJMDeer Creek Solar Facility
Deer Creek Solar Facility is a 2.5 MW solar request built and operating in the PJM interconnection queue, in Grant County, Indiana, connecting to AEP.
Request details
- Queue ID
- Z2-115
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- AEP
- Connection point (POI)
- Deer Creek 12.47kV
- Location
- Grant County, Indiana
- Technology
- Solar: 2.5 MW
- Total requested
- 2.5 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Wholesale Market P
- Queue status
- Operational
- Entered queue
- 30 April 2014
- Proposed online date
- March 2016
- Came online
- January 2016
Location
Marker shows the centre of Grant County; the queue data does not give exact sites.
Other requests in Grant County
- BR Solar Sheriff 1Solar · 75.0 MW · agreement signed
- Solar + storage project AI1-134, Grant CountySolar + storage · 200 MW · in study
- Solar + storage project AG2-191, Grant CountySolar + storage · 30.0 MW · in study
- Solar + storage project AG2-192, Grant CountySolar + storage · 19.0 MW · in study
- Golden Aster Solar Energy CenterSolar · 160 MW · suspended
- Golden Aster Solar Energy CenterBattery storage · 40.0 MW · suspended
- Solar project J2251, Grant CountySolar · 200 MW · withdrawn
- Solar + storage project AF2-204, Grant CountySolar + storage · 110 MW · withdrawn
- Solar + storage project AG2-412, Grant CountySolar + storage · 100 MW · withdrawn
- Solar + storage project AG2-546, Grant CountySolar + storage · 40.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem