United States › Grid › Interconnection queues › Indiana

BATTERY STORAGE · PJM

Golden Aster Solar Energy Center

Golden Aster Solar Energy Center is a 40.0 MW battery storage request suspended in the PJM interconnection queue, in Grant County, Indiana, connecting to AEP.

Queue statusPaused / redesign
  1. PlanningQueued Mar 2019 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget May 2026 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
AE2-172
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Connection point (POI)
Mississinewa-Gaston 138 kV
Location
Grant County, Indiana
Technology
Battery: 40.0 MW
Total requested
40.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Suspended
Entered queue
16 March 2019
Proposed online date
May 2026

Location

Marker shows the centre of Grant County; the queue data does not give exact sites.

Power plants in Indiana · Transmission lines in Indiana

Other requests in Grant County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem