United States › Grid › Interconnection queues › Indiana
SOLAR + STORAGE · PJMSolar + storage project AG2-519, Delaware County
Solar + storage project AG2-519, Delaware County is a 66.5 MW solar + storage request in interconnection study in the PJM interconnection queue, in Delaware County, Indiana, connecting to AEP.
Queue statusIn planning
- PlanningQueued Mar 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Feb 2024 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- AG2-519
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- AEP
- Developer
- Muncie Solar 1, LLC
- Connection point (POI)
- Royerton - Desoto 138 kV
- Location
- Delaware County, Indiana
- Technology
- Solar: 66.5 MW · Battery
- Total requested
- 66.5 MW
- Service type
- Network resource (NRIS)
- Study phase
- System Impact Study
- Queue status
- Active
- Entered queue
- 13 March 2025
- Proposed online date
- February 2024
Location
Marker shows the centre of Delaware County; the queue data does not give exact sites.
Other requests in Delaware County
- Hawthorn SolarSolar · 83.0 MW · agreement signed
- Solar project AI2-115, Delaware CountySolar · 84.0 MW · in study
- Meadow Forge Solar Energy CenterSolar · 130 MW · suspended
- Meadow Forge Solar Energy CenterSolar · 33.0 MW · suspended
- Solar project AE1-217, Delaware CountySolar · 200 MW · withdrawn
- Solar project AF1-298, Delaware CountySolar · 200 MW · withdrawn
- Onshore wind project V3-053, Delaware CountyOnshore wind · 150 MW · withdrawn
- Esker Solar ParkSolar · 140 MW · withdrawn
- Solar project AH1-607, Delaware CountySolar · 119 MW · withdrawn
- Esker Solar Park IISolar · 100 MW · withdrawn
- Royerton Solar and StorageSolar · 100 MW · withdrawn
- Battery storage project AE2-170, Delaware CountyBattery storage · 50.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem