ONSHORE WIND Β· PJMOnshore wind project V3-053, Delaware County
Onshore wind project V3-053, Delaware County is a 150 MW onshore wind request withdrawn in the PJM interconnection queue, in Delaware County, Indiana, connecting to AEP.
Queue statusWithdrawn / abandoned
- PlanningQueued Oct 2009 (completed)
- Withdrawn / abandonedOct 2013 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- V3-053
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- AEP
- Connection point (POI)
- Desoto 138kV
- Location
- Delaware County, Indiana
- Technology
- Wind: 150 MW
- Total requested
- 150 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
- Queue status
- Withdrawn
- Entered queue
- 22 October 2009
- Proposed online date
- December 2013
- Withdrawn
- October 2013
Location
Marker shows the centre of Delaware County; the queue data does not give exact sites.
Other requests in Delaware County
- Hawthorn SolarSolar Β· 83.0 MW Β· agreement signed
- Solar project AI2-115, Delaware CountySolar Β· 84.0 MW Β· in study
- Solar + storage project AG2-519, Delaware CountySolar + storage Β· 66.5 MW Β· in study
- Meadow Forge Solar Energy CenterSolar Β· 130 MW Β· suspended
- Meadow Forge Solar Energy CenterSolar Β· 33.0 MW Β· suspended
- Solar project AE1-217, Delaware CountySolar Β· 200 MW Β· withdrawn
- Solar project AF1-298, Delaware CountySolar Β· 200 MW Β· withdrawn
- Esker Solar ParkSolar Β· 140 MW Β· withdrawn
- Solar project AH1-607, Delaware CountySolar Β· 119 MW Β· withdrawn
- Esker Solar Park IISolar Β· 100 MW Β· withdrawn
- Royerton Solar and StorageSolar Β· 100 MW Β· withdrawn
- Battery storage project AE2-170, Delaware CountyBattery storage Β· 50.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem