United States › Grid › Interconnection queues › Indiana

SOLAR · MISO

Solar project J1736, Dubois County

Solar project J1736, Dubois County is a 100 MW solar request in interconnection study in the MISO interconnection queue, in Dubois County, Indiana, connecting to Southern Indiana Gas & Electric Company d/b/a Centerpoint Energy Indiana South.

Queue statusIn planning
  1. PlanningQueued Jun 2020 (current stage)
  2. ConsentedJun 2025 (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Aug 2023 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J1736
Grid region
MISO (Midcontinent)
Utility / transmission owner
Southern Indiana Gas & Electric Company d/b/a Centerpoint Energy Indiana South
Connection point (POI)
Duff 138kV
Location
Dubois County, Indiana
Technology
Solar: 100 MW
Total requested
100 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA In Process; Post GIA Status: Not Started
Queue status
Active
Entered queue
22 June 2020
Agreement signed
25 June 2025
Proposed online date
August 2023

Location

Marker shows the centre of Dubois County; the queue data does not give exact sites.

Power plants in Indiana · Transmission lines in Indiana

Other requests in Dubois County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem