United States › Grid › Interconnection queues › Indiana
ONSHORE WIND · MISOOnshore wind project J2048, Benton County
Onshore wind project J2048, Benton County is a 100 MW onshore wind request in interconnection study in the MISO interconnection queue, in Benton County, Indiana, connecting to NORTHERN INDIANA PUBLIC SERVICE COMPANY.
- PlanningQueued Mar 2022 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Sep 2025 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J2048
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- NORTHERN INDIANA PUBLIC SERVICE COMPANY
- Connection point (POI)
- GOODLAND - MORRISON DITCH 138.0kV
- Location
- Benton County, Indiana
- Technology
- Wind: 100 MW
- Total requested
- 100 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 2; Post GIA Status: Not Started
- Queue status
- Active
- Entered queue
- 25 March 2022
- Proposed online date
- September 2025
Location
Marker shows the centre of Benton County; the queue data does not give exact sites.
Other requests in Benton County
- Onshore wind project J1470, Benton CountyOnshore wind · 30.0 MW · agreement signed
- Onshore wind project J2440, Benton CountyOnshore wind · 100 MW · in study
- Fowler Ridge WFOnshore wind · 500 MW · built
- Onshore wind project J515, Benton CountyOnshore wind · 400 MW · built
- Fowler Ridge 4 WFOnshore wind · 250 MW · built
- Meadow Lake WF II, Meadow Lake WF IIIOnshore wind · 200 MW · built
- Onshore wind project J431, Benton CountyOnshore wind · 100 MW · built
- Onshore wind project N001, Benton CountyOnshore wind · 100 MW · built
- Onshore wind project G439, Benton CountyOnshore wind · 100 MW · built
- Onshore wind project G606, Benton CountyOnshore wind · 30.0 MW · built
- Onshore wind project AD2-015, Benton CountyOnshore wind · 500 MW · withdrawn
- Onshore wind project AD1-137, Benton CountyOnshore wind · 500 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem