🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Indiana

ONSHORE WIND · MISO

Onshore wind project G439, Benton County

Onshore wind project G439, Benton County is a 100 MW onshore wind request built and operating in the MISO interconnection queue, in Benton County, Indiana.

Queue statusOperating
  1. PlanningQueued Jul 2004 (completed)
  2. ConsentedApr 2007 (completed)
  3. Construction (completed)
  4. OperatingDec 2005 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
G439
Grid region
MISO (Midcontinent)
Connection point (POI)
Morrison Ditch 138 kV
Location
Benton County, Indiana
Technology
Wind: 100 MW
Total requested
100 MW
Study phase
Network Upgrade
Queue status
Operational
Entered queue
29 July 2004
Agreement signed
5 April 2007
Proposed online date
December 2005
Came online
December 2005

Location

Marker shows the centre of Benton County; the queue data does not give exact sites.

Power plants in Indiana · Transmission lines in Indiana

Other requests in Benton County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem