United States β€Ί Grid β€Ί Interconnection queues β€Ί Indiana

ONSHORE WIND Β· PJM

Onshore wind project AD2-015, Benton County

Onshore wind project AD2-015, Benton County is a 500 MW onshore wind request withdrawn in the PJM interconnection queue, in Benton County, Indiana, connecting to AEP.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2017 (completed)
  2. Withdrawn / abandonedJan 2018 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AD2-015
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Connection point (POI)
Dequine 345 kV
Location
Benton County, Indiana
Technology
Wind: 500 MW
Total requested
500 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
13 November 2017
Proposed online date
December 2020
Withdrawn
January 2018

Location

Marker shows the centre of Benton County; the queue data does not give exact sites.

Power plants in Indiana Β· Transmission lines in Indiana

Other requests in Benton County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem