United States › Grid › Interconnection queues › Indiana

ONSHORE WIND · PJM

Headwaters Wind Farm III

Headwaters Wind Farm III is a 100 MW onshore wind request suspended in the PJM interconnection queue, in Randolph County, Indiana, connecting to AEP.

Queue statusPaused / redesign
  1. PlanningQueued Sep 2018 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget May 2026 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
AE1-209
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Connection point (POI)
Desoto 345 kV
Location
Randolph County, Indiana
Technology
Wind: 100 MW
Total requested
100 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Suspended
Entered queue
27 September 2018
Proposed online date
May 2026

Location

Marker shows the centre of Randolph County; the queue data does not give exact sites.

Power plants in Indiana · Transmission lines in Indiana

Other requests in Randolph County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem