United States βΊ Grid βΊ Interconnection queues βΊ Indiana
SOLAR Β· PJMMadison County Solar
Madison County Solar is a 100 MW solar request suspended in the PJM interconnection queue, in Madison County, Indiana, connecting to AEP.
Queue statusPaused / redesign
- PlanningQueued Mar 2018 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Sep 2025 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- AD2-071
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- AEP
- Connection point (POI)
- Strawton-Deer Creek 138 kV
- Location
- Madison County, Indiana
- Technology
- Solar: 100 MW
- Total requested
- 100 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
- Queue status
- Suspended
- Entered queue
- 15 March 2018
- Proposed online date
- September 2025
Location
Marker shows the centre of Madison County; the queue data does not give exact sites.
Other requests in Madison County
- Battery storage project J1357, Madison CountyBattery storage Β· 150 MW Β· agreement signed
- Fall Creek Energy StorageBattery storage Β· 80.0 MW Β· agreement signed
- Solar project AI2-152, Madison CountySolar Β· 28.8 MW Β· in study
- Wildcat Wind Farm IOnshore wind Β· 200 MW Β· built
- Onshore wind project U4-039, Madison CountyOnshore wind Β· 710 MW Β· withdrawn
- Liberty II StorageBattery storage Β· 300 MW Β· withdrawn
- Gas project J3831, Madison CountyGas Β· 240 MW Β· withdrawn
- Solar project AH1-400, Madison CountySolar Β· 150 MW Β· withdrawn
- Lone Oak SolarSolar Β· 120 MW Β· withdrawn
- Solar project AD1-139, Madison CountySolar Β· 100 MW Β· withdrawn
- Battery storage project J1731, Madison CountyBattery storage Β· 100 MW Β· withdrawn
- Onshore wind project U4-038, Madison CountyOnshore wind Β· 100 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem