United States › Grid › Interconnection queues › Indiana
BATTERY STORAGE · PJMLiberty II Storage
Liberty II Storage is a 300 MW battery storage request withdrawn in the PJM interconnection queue, in Madison County, Indiana, connecting to AEP.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2020 (completed)
- Withdrawn / abandonedJan 2026 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AF2-407
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- AEP
- Developer
- Liberty Madison Storage LLC
- Connection point (POI)
- Fall Creek 345 kV
- Location
- Madison County, Indiana
- Technology
- Battery: 300 MW
- Total requested
- 300 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Withdrawn
- Queue status
- Withdrawn
- Entered queue
- 31 March 2020
- Proposed online date
- June 2022
- Withdrawn
- January 2026
Location
Marker shows the centre of Madison County; the queue data does not give exact sites.
Other requests in Madison County
- Battery storage project J1357, Madison CountyBattery storage · 150 MW · agreement signed
- Fall Creek Energy StorageBattery storage · 80.0 MW · agreement signed
- Solar project AI2-152, Madison CountySolar · 28.8 MW · in study
- Madison County SolarSolar · 100 MW · suspended
- Wildcat Wind Farm IOnshore wind · 200 MW · built
- Onshore wind project U4-039, Madison CountyOnshore wind · 710 MW · withdrawn
- Gas project J3831, Madison CountyGas · 240 MW · withdrawn
- Solar project AH1-400, Madison CountySolar · 150 MW · withdrawn
- Lone Oak SolarSolar · 120 MW · withdrawn
- Solar project AD1-139, Madison CountySolar · 100 MW · withdrawn
- Battery storage project J1731, Madison CountyBattery storage · 100 MW · withdrawn
- Onshore wind project U4-038, Madison CountyOnshore wind · 100 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem