United States › Grid › Interconnection queues › Indiana
ONSHORE WIND · PJMWildcat Wind Farm I
Wildcat Wind Farm I is a 200 MW onshore wind request built and operating in the PJM interconnection queue, in Madison County, Indiana, connecting to AEP.
Request details
- Queue ID
- U3-002
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- AEP
- Connection point (POI)
- Deer Creek-Fisher Body-Mullin 138kV
- Location
- Madison County, Indiana
- Technology
- Wind: 200 MW
- Total requested
- 200 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Document Posted
- Queue status
- Operational
- Entered queue
- 13 August 2008
- Agreement signed
- 2 June 2011
- Proposed online date
- December 2012
- Came online
- December 2012
Location
Marker shows the centre of Madison County; the queue data does not give exact sites.
Other requests in Madison County
- Battery storage project J1357, Madison CountyBattery storage · 150 MW · agreement signed
- Fall Creek Energy StorageBattery storage · 80.0 MW · agreement signed
- Solar project AI2-152, Madison CountySolar · 28.8 MW · in study
- Madison County SolarSolar · 100 MW · suspended
- Onshore wind project U4-039, Madison CountyOnshore wind · 710 MW · withdrawn
- Liberty II StorageBattery storage · 300 MW · withdrawn
- Gas project J3831, Madison CountyGas · 240 MW · withdrawn
- Solar project AH1-400, Madison CountySolar · 150 MW · withdrawn
- Lone Oak SolarSolar · 120 MW · withdrawn
- Solar project AD1-139, Madison CountySolar · 100 MW · withdrawn
- Battery storage project J1731, Madison CountyBattery storage · 100 MW · withdrawn
- Onshore wind project U4-038, Madison CountyOnshore wind · 100 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem