United States › Grid › Interconnection queues › Indiana

BATTERY STORAGE · MISO

Battery storage project J1357, Madison County

Battery storage project J1357, Madison County is a 150 MW battery storage request with a signed interconnection agreement in the MISO interconnection queue, in Madison County, Indiana, connecting to DUKE ENERGY INDIANA.

Queue statusConsented
  1. PlanningQueued Apr 2019 (completed)
  2. ConsentedJan 2023 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Sep 2025 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
J1357
Grid region
MISO (Midcontinent)
Utility / transmission owner
DUKE ENERGY INDIANA
Connection point (POI)
Madison 138 KV SUBSTATION
Location
Madison County, Indiana
Technology
Battery: 150 MW
Total requested
150 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: Not Started
Queue status
Active
Entered queue
29 April 2019
Agreement signed
31 January 2023
Proposed online date
September 2025

Location

Marker shows the centre of Madison County; the queue data does not give exact sites.

Power plants in Indiana · Transmission lines in Indiana

Other requests in Madison County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem