United States › Grid › Interconnection queues › Indiana
BATTERY STORAGE · MISOBattery storage project J1357, Madison County
Battery storage project J1357, Madison County is a 150 MW battery storage request with a signed interconnection agreement in the MISO interconnection queue, in Madison County, Indiana, connecting to DUKE ENERGY INDIANA.
Queue statusConsented
- PlanningQueued Apr 2019 (completed)
- ConsentedJan 2023 (current stage)
- Construction (not yet reached)
- OperatingTarget Sep 2025 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- J1357
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- DUKE ENERGY INDIANA
- Connection point (POI)
- Madison 138 KV SUBSTATION
- Location
- Madison County, Indiana
- Technology
- Battery: 150 MW
- Total requested
- 150 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA; Post GIA Status: Not Started
- Queue status
- Active
- Entered queue
- 29 April 2019
- Agreement signed
- 31 January 2023
- Proposed online date
- September 2025
Location
Marker shows the centre of Madison County; the queue data does not give exact sites.
Other requests in Madison County
- Fall Creek Energy StorageBattery storage · 80.0 MW · agreement signed
- Solar project AI2-152, Madison CountySolar · 28.8 MW · in study
- Madison County SolarSolar · 100 MW · suspended
- Wildcat Wind Farm IOnshore wind · 200 MW · built
- Onshore wind project U4-039, Madison CountyOnshore wind · 710 MW · withdrawn
- Liberty II StorageBattery storage · 300 MW · withdrawn
- Gas project J3831, Madison CountyGas · 240 MW · withdrawn
- Solar project AH1-400, Madison CountySolar · 150 MW · withdrawn
- Lone Oak SolarSolar · 120 MW · withdrawn
- Solar project AD1-139, Madison CountySolar · 100 MW · withdrawn
- Battery storage project J1731, Madison CountyBattery storage · 100 MW · withdrawn
- Onshore wind project U4-038, Madison CountyOnshore wind · 100 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem