| Project | Capacity | Status |
|---|---|---|
| Carol Solar Solar |
223 MW | Paused / redesign |
| Olympic BESS Battery storage · SMT Olympic BESS LLC |
223 MW | In study |
| Oystercatcher Solar Solar · Oystercatcher Solar, LLC |
222 MW | Agreement signed |
| Utley Solar Solar |
222 MW | Paused / redesign |
| Grayback Solar Solar · Grayback Solar, LLC |
222 MW | In study |
| Miracle Ranch Solar SLF Solar + storage · Miracle Ranch LLC |
222 MW | In study |
| Goodalta Solar Solar · GoodAlta Power Center LLC |
221 MW | In study |
| Douie Solar Solar · Buffalo Spring Solar LLC |
221 MW | In study |
| Angel City Solar Solar · Angel City Energy Center, LLC |
221 MW | In study |
| Shoshana Storage Battery storage · Shoshana Storage Project LLC |
221 MW | In study |
| Solar Star Rhome Storage Battery storage · Solar Star Rhome Storage |
221 MW | In study |
| Coke BESS Battery storage · Coke ESS, LLC |
220 MW | In study |
| Crowded Star Solar Solar + storage · Jones City Solar, LLC |
219 MW | Agreement signed |
| Sepanta Solar Solar · BREG - Belgian Renewable Energy Group |
217 MW | In study |
| Two Barbaras BESS Battery storage · Two Barbaras BESS |
217 MW | Agreement signed |
| Pez Rojo BESS Battery storage · Pez Rojo BESS, LLC |
217 MW | In study |
| Maratua Solar Solar · BDPU Solar Maratua, LLC |
217 MW | Paused / redesign |
| Gas project ERAS-2025-002, Hale County Gas |
217 MW | In study |
| Marcos Solar SLF Solar + storage · GRS BESS Texas Eight |
216 MW | In study |
| Walleye Solar Solar · Sandow Lakes Ranch Solar II, LLC |
215 MW | In study |
| Diamond Sage Solar 1 Solar + storage · DGC Renewables, LLC |
214 MW | In study |
| Diamond Sage Solar 2 Solar + storage · DGC Renewables, LLC |
214 MW | In study |
| Puerto Del Sol 2 Solar · PUERTO DEL SOL, LLC |
214 MW | In study |
| Puerto Del Sol 1 Solar · PUERTO DEL SOL, LLC |
214 MW | In study |
| Mesquite Creek Windpower Repower Onshore wind · Mesquite Creek Wind LLC |
213 MW | In study |
| BumbleBee Solar Solar · BumbleBee Solar Farm LLC |
212 MW | In study |
| Rock Rose BESS Battery storage · Rock Rose Energy Storage LLC |
212 MW | Agreement signed |
| Vazlon Solar SLF Solar + storage · Vazlon Energy LLC |
211 MW | In study |
| Grimes County Solar Solar · Grimes County Solar Project, LLC |
211 MW | Agreement signed |
| Rockridge Solar Solar · Magnolia Solar Development LLC |
211 MW | Agreement signed |
| Gypsum Plains Storage Solar + storage · Gypsum Plains Solar, LLC |
211 MW | In study |
| Bessie Storage Battery storage · Bessie Energy Storage, LLC |
211 MW | In study |
| Cumulus Grid BESS Battery storage · Cumulus Grid, LLC |
211 MW | Agreement signed |
| Val Vista Grid BESS 2 Battery storage · Val Vista Grid, LLC |
211 MW | In study |
| Guadalupe Battery Storage Project Battery storage · Guadalupe Power Partners, LP |
211 MW | In study |
| Freestone Battery Storage Project Battery storage · Freestone Power Generation, LLC |
211 MW | In study |
| Leon Solar Park Solar + storage · Misae Solar IV LLC |
210 MW | Agreement signed |
| Elk Unit 4 Gas · Golden Spread Electric Cooperative, Inc. |
210 MW | In study |
| Alamosa Solar Solar |
210 MW | Paused / redesign |
| Val Vista Grid BESS 1 Battery storage · Val Vista Grid, LLC |
209 MW | In study |
| New Hickory Solar Solar · New Hickory Solar LLC |
209 MW | Agreement signed |
| Moonlit Bayou Storage Battery storage · Moonlit Bayou Energy Center, LLC |
209 MW | In study |
| Treehouse Storage Solar + storage · Treehouse Solar, LLC |
209 MW | In study |
| Anila BESS Solar + storage · Alina Energy LLC |
209 MW | Agreement signed |
| Hornet Solar II SLF Solar + storage · Hornet Solar II LLC |
209 MW | Agreement signed |
| Clapton Storage Solar + storage · Clapton BESS |
209 MW | In study |
| Sorghum BESS Battery storage · Blue Creek BESS, LLC |
209 MW | Agreement signed |
| Sisters Storage Solar + storage · 174 Power Global Properties |
209 MW | In study |
| Starlit Pasture Storage Battery storage · Starlit Pasture Energy Center, LLC |
209 MW | In study |
| Revolution BESS Battery storage · Nova Clean Energy LLC |
209 MW | In study |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- ERCOT (Texas)1,976 · 447.2 GW
- SPP (Southwest Power Pool)79 · 20.6 GW
- MISO (Midcontinent)27 · 6,659 MW
- West (non-ISO utilities)12 · 1,947 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)