🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

SOLAR + STORAGE · ERCOT

Crowded Star Solar

Crowded Star Solar is a 219 MW solar + storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Jones County, Texas.

Queue statusConsented
  1. PlanningQueued Jan 2019 (completed)
  2. ConsentedJul 2023 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Jul 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
20INR0241
Grid region
ERCOT (Texas)
Developer
Jones City Solar, LLC
Connection point (POI)
tap 345kV 68001 Claytonville – 68004 Phantom Hill c2 (New Substation: Open Sky 68014)
Location
Jones County, Texas
Technology
Solar: 219 MW · Battery
Total requested
219 MW
Study phase
SS Completed, FIS Completed, IA
Queue status
Active
Entered queue
21 January 2019
Agreement signed
27 July 2023
Proposed online date
July 2026

Location

Marker shows the centre of Jones County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Jones County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem