United States › Grid › Interconnection queues › Texas

SOLAR + STORAGE · ERCOT

Crowded Star I BESS

Crowded Star I BESS is a 203 MW solar + storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Jones County, Texas.

Queue statusConsented
  1. PlanningQueued Aug 2023 (completed)
  2. ConsentedDec 2025 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Jul 2027 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
25INR0473
Grid region
ERCOT (Texas)
Developer
Jones City Solar II, LLC
Connection point (POI)
68014 Open Sky
Location
Jones County, Texas
Technology
Battery: 203 MW · Battery
Total requested
203 MW
Study phase
SS Completed, FIS Completed, IA
Queue status
Active
Entered queue
21 August 2023
Agreement signed
1 December 2025
Proposed online date
July 2027

Location

Marker shows the centre of Jones County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Jones County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem