United States › Grid › Interconnection queues › Texas

SOLAR · ERCOT

Goodalta Solar

Goodalta Solar is a 221 MW solar request in interconnection study in the ERCOT interconnection queue, in Navarro County, Texas.

Queue statusIn planning
  1. PlanningQueued Jan 2021 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Sep 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
23INR0171
Grid region
ERCOT (Texas)
Developer
GoodAlta Power Center LLC
Connection point (POI)
tap 138kV 3127 Trinidad - 212 Winkler
Location
Navarro County, Texas
Technology
Solar: 221 MW
Total requested
221 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
25 January 2021
Proposed online date
September 2027

Location

Marker shows the centre of Navarro County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Navarro County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem