United States › Grid › Interconnection queues › Texas
BATTERY STORAGE · ERCOTCape Rich BESS
Cape Rich BESS is a 151 MW battery storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Navarro County, Texas.
Queue statusConsented
- PlanningQueued Jul 2023 (completed)
- ConsentedFeb 2025 (current stage)
- Construction (not yet reached)
- OperatingTarget Apr 2028 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 26INR0180
- Grid region
- ERCOT (Texas)
- Developer
- Cape Rich BESS
- Connection point (POI)
- 3387 Revolution Switch 138kV
- Location
- Navarro County, Texas
- Technology
- Battery: 151 MW
- Total requested
- 151 MW
- Study phase
- SS Completed, FIS Completed, IA
- Queue status
- Active
- Entered queue
- 10 July 2023
- Agreement signed
- 3 February 2025
- Proposed online date
- April 2028
Location
Marker shows the centre of Navarro County; the queue data does not give exact sites.
Other requests in Navarro County
- Tehuacana Creek SolarSolar + storage · 505 MW · agreement signed
- Tormes SolarSolar · 357 MW · agreement signed
- Three Canes Solar SLFSolar · 333 MW · agreement signed
- Board Creek WindOnshore wind · 299 MW · agreement signed
- Yellow Cat WindOnshore wind · 262 MW · agreement signed
- Glasgow SolarSolar + storage · 204 MW · agreement signed
- Armadillo SolarSolar · 200 MW · agreement signed
- Bluebonnet Prairie WindOnshore wind · 173 MW · agreement signed
- Gaia SolarSolar + storage · 144 MW · agreement signed
- Glasgow StorageSolar + storage · 101 MW · agreement signed
- Gaia StorageSolar + storage · 78.8 MW · agreement signed
- Wildflower StorageBattery storage · 359 MW · in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem