BATTERY STORAGE · ERCOT

Cape Rich BESS

Cape Rich BESS is a 151 MW battery storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Navarro County, Texas.

Queue statusConsented
  1. PlanningQueued Jul 2023 (completed)
  2. ConsentedFeb 2025 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Apr 2028 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
26INR0180
Grid region
ERCOT (Texas)
Developer
Cape Rich BESS
Connection point (POI)
3387 Revolution Switch 138kV
Location
Navarro County, Texas
Technology
Battery: 151 MW
Total requested
151 MW
Study phase
SS Completed, FIS Completed, IA
Queue status
Active
Entered queue
10 July 2023
Agreement signed
3 February 2025
Proposed online date
April 2028

Location

Marker shows the centre of Navarro County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Navarro County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem