United States βΊ Grid βΊ Interconnection queues βΊ Texas
SOLAR Β· ERCOTUtley Solar
Utley Solar is a 222 MW solar request suspended in the ERCOT interconnection queue, in Freestone County, Texas.
Queue statusPaused / redesign
- PlanningQueued Sep 2021 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Apr 2025 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 24INR0117
- Grid region
- ERCOT (Texas)
- Location
- Freestone County, Texas
- Technology
- Solar: 222 MW
- Total requested
- 222 MW
- Queue status
- Suspended
- Entered queue
- 6 September 2021
- Proposed online date
- April 2025
Location
Marker shows the centre of Freestone County; the queue data does not give exact sites.
Other requests in Freestone County
- Piedra SolarSolar + storage Β· 282 MW Β· agreement signed
- Pin Peaking Energy Center 1 (TEF- Due Diligence)Gas Β· 228 MW Β· agreement signed
- Pin Peaking Energy Center 2 (TEF- Due Diligence)Gas Β· 228 MW Β· agreement signed
- Bar Candela Solar SLFSolar + storage Β· 200 MW Β· agreement signed
- Fairway StorageBattery storage Β· 120 MW Β· agreement signed
- Piedra BESSSolar + storage Β· 104 MW Β· agreement signed
- Jewett Energy Center 1 GasGas Β· 1,274 MW Β· in study
- Silver Dollar SolarSolar + storage Β· 302 MW Β· in study
- Amerada SolarSolar + storage Β· 302 MW Β· in study
- Simsboro StorageBattery storage Β· 302 MW Β· in study
- Douie SolarSolar Β· 221 MW Β· in study
- Freestone Battery Storage ProjectBattery storage Β· 211 MW Β· in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem