Requests shown602,202 MW
Active in queue129 MW5 requests
Agreement signed90.0 MW3 requests
Withdrawn602,202 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

60 requests Β· page 1 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Solar
Solar
196 MWWithdrawn / abandoned Franklin, VTISO-NE Sep 2015target 2017
Battery Storage
Battery storage
180 MWWithdrawn / abandoned Windsor, VTISO-NE Apr 2023target 2027
Combined Cycle
Other
124 MWWithdrawn / abandoned Orleans, VTISO-NE Aug 2005target 2010
Battery Storage
Battery storage
115 MWWithdrawn / abandoned Windsor, VTISO-NE Apr 2024target 2028
Battery Storage
Battery storage
105 MWWithdrawn / abandoned Windsor, VTISO-NE Apr 2023target 2027
Battery Storage
Battery storage
101 MWWithdrawn / abandoned Windham, VTISO-NE Jun 2024target 2027
Wind
Onshore wind
85.0 MWWithdrawn / abandoned Rutland, VTISO-NE Oct 2008target 2011
Wind
Onshore wind
73.5 MWWithdrawn / abandoned Windham, VTISO-NE Dec 2014target 2019
Wind
Onshore wind
60.0 MWWithdrawn / abandoned Caledonia, VTISO-NE Jan 2012target 2015
Wind Project
Onshore wind
60.0 MWWithdrawn / abandoned Rutland, VTISO-NE Sep 2006target 2010
Wind Project
Onshore wind
53.0 MWWithdrawn / abandoned Caledonia, VTISO-NE May 2005target 2007
Wind Project
Onshore wind
48.0 MWWithdrawn / abandoned Windham, VTISO-NE Dec 2005target 2008
Gas Turbine
Gas
47.5 MWWithdrawn / abandoned Chittenden, VTISO-NE Mar 2014target 2018
Wind Project
Onshore wind
45.0 MWWithdrawn / abandoned Bennington, VTISO-NE Aug 2005target 2010
Biomass
Other
37.0 MWWithdrawn / abandoned Windsor, VTISO-NE May 2013target 2015
Wind Repower
Onshore wind
35.2 MWWithdrawn / abandoned Caledonia, VTISO-NE Dec 2023target 2026
Wind
Onshore wind
34.0 MWWithdrawn / abandoned Orleans, VTISO-NE Jun 2008target 2011
Fair Haven Biomass
Other
33.0 MWWithdrawn / abandoned Rutland, VTISO-NE May 2010target 2016
Biomass
Other
33.0 MWWithdrawn / abandoned Bennington, VTISO-NE Jun 2010target 2013
Biomass
Other
30.0 MWWithdrawn / abandoned Windsor, VTISO-NE Feb 2009target 2011
Biomass
Other
30.0 MWWithdrawn / abandoned Windsor, VTISO-NE Sep 2008target 2011
Deerfield Wind
Onshore wind
30.0 MWWithdrawn / abandoned Bennington, VTISO-NE Sep 2008target 2013
GMP Generator Replacement
Gas
29.5 MWWithdrawn / abandoned Chittenden, VTISO-NE Aug 2008target 2014
Biomass
Other
27.5 MWWithdrawn / abandoned Windsor, VTISO-NE Feb 2006target 2009
Biomass
Other
27.5 MWWithdrawn / abandoned Windsor, VTISO-NE Aug 2006target 2009
Solar
Solar
22.5 MWWithdrawn / abandoned Rutland, VTISO-NE Apr 2018target 2020
Solar
Solar
20.1 MWWithdrawn / abandoned Franklin, VTISO-NE Apr 2017target 2018
Solar
Solar
20.1 MWWithdrawn / abandoned Franklin, VTISO-NE Apr 2017target 2019
Solar
Solar
20.1 MWWithdrawn / abandoned Orange, VTISO-NE Apr 2017target 2019
Solar
Solar
20.0 MWWithdrawn / abandoned Orange, VTISO-NE Apr 2018target 2021
Solar
Solar
20.0 MWWithdrawn / abandoned Orleans, VTISO-NE Aug 2015target 2017
solar
Solar
20.0 MWWithdrawn / abandoned Franklin, VTISO-NE Aug 2015target 2016
Grandpas Knob Wind
Onshore wind
20.0 MWWithdrawn / abandoned Rutland, VTISO-NE Mar 2011target 2016
Battery Storage
Battery storage
20.0 MWWithdrawn / abandoned Addison, VTISO-NE Apr 2021target 2022
Solar
Solar
20.0 MWWithdrawn / abandoned Orange, VTISO-NE Aug 2015target 2016
solar
Solar
20.0 MWWithdrawn / abandoned Windsor, VTISO-NE Aug 2015target 2016
Solar
Solar
20.0 MWWithdrawn / abandoned Franklin, VTISO-NE Aug 2015target 2017
Solar
Solar
20.0 MWWithdrawn / abandoned Windham, VTISO-NE Jul 2017target 2022
Solar
Solar
20.0 MWWithdrawn / abandoned Franklin, VTISO-NE Apr 2018target 2021
wind
Onshore wind
20.0 MWWithdrawn / abandoned Franklin, VTISO-NE Jul 2017target 2020
Solar
Solar
20.0 MWWithdrawn / abandoned Rutland, VTISO-NE Sep 2015target 2016
Solar
Solar
20.0 MWWithdrawn / abandoned Franklin, VTISO-NE Apr 2018target 2021
Solar
Solar
19.9 MWWithdrawn / abandoned Rutland, VTISO-NE Sep 2015target 2016
Solar
Solar
19.9 MWWithdrawn / abandoned Franklin, VTISO-NE Jun 2015target 2016
Solar
Solar
19.9 MWWithdrawn / abandoned Windsor, VTISO-NE Jul 2016target 2017
Solar
Solar
19.9 MWWithdrawn / abandoned Windsor, VTISO-NE Jun 2015target 2016
Solar
Solar
19.9 MWWithdrawn / abandoned Franklin, VTISO-NE Sep 2015target 2016
wind
Onshore wind
17.4 MWWithdrawn / abandoned Franklin, VTISO-NE Feb 2015target 2016
Battery Storage
Battery storage
16.0 MWWithdrawn / abandoned Chittenden, VTISO-NE Aug 2024target 2026
Davenport Solar
Solar
15.0 MWWithdrawn / abandoned Rutland, VTISO-NE Apr 2018target 2021
Page 1 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)