United States › Grid › Interconnection queues › Vermont
BATTERY STORAGE · ISO-NEBattery Storage
Battery Storage is a 16.0 MW battery storage request withdrawn in the ISO-NE interconnection queue, in Chittenden County, Vermont.
Queue statusWithdrawn / abandoned
- PlanningQueued Aug 2024 (completed)
- Withdrawn / abandonedJun 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 1586
- Grid region
- ISO-NE (New England)
- Connection point (POI)
- Global Foundries 13.8 kV bus
- Location
- Chittenden County, Vermont
- Technology
- Battery: 16.0 MW
- Total requested
- 16.0 MW
- Queue status
- Withdrawn
- Entered queue
- 14 August 2024
- Proposed online date
- April 2026
- Withdrawn
- June 2025
Location
Marker shows the centre of Chittenden County; the queue data does not give exact sites.
Other requests in Chittenden County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem