United States βΊ Grid βΊ Interconnection queues βΊ Vermont
GAS Β· ISO-NEGas Turbine
Gas Turbine is a 47.5 MW gas request withdrawn in the ISO-NE interconnection queue, in Chittenden County, Vermont.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2014 (completed)
- Withdrawn / abandonedMar 2014 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 446
- Grid region
- ISO-NE (New England)
- Connection point (POI)
- Gorge substation, No. 16, Breaker 3320.
- Location
- Chittenden County, Vermont
- Technology
- Gas: 47.5 MW Β· Oil
- Total requested
- 47.5 MW
- Service type
- Network resource (NRIS)
- Queue status
- Withdrawn
- Entered queue
- 4 March 2014
- Proposed online date
- May 2018
- Withdrawn
- March 2014
Location
Marker shows the centre of Chittenden County; the queue data does not give exact sites.
Other requests in Chittenden County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem