United States › Grid › Interconnection queues › Vermont
GAS · ISO-NEGMP Generator Replacement
GMP Generator Replacement is a 29.5 MW gas request withdrawn in the ISO-NE interconnection queue, in Chittenden County, Vermont.
Queue statusWithdrawn / abandoned
- PlanningQueued Aug 2008 (completed)
- Withdrawn / abandonedOct 2012 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 274
- Grid region
- ISO-NE (New England)
- Connection point (POI)
- GMP Gorge Substation
- Location
- Chittenden County, Vermont
- Technology
- Gas: 29.5 MW · Oil
- Total requested
- 29.5 MW
- Service type
- Network resource (NRIS)
- Study phase
- System Impact Study
- Queue status
- Withdrawn
- Entered queue
- 7 August 2008
- Proposed online date
- June 2014
- Withdrawn
- October 2012
Location
Marker shows the centre of Chittenden County; the queue data does not give exact sites.
Other requests in Chittenden County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem