OTHER Β· ISO-NE

Combined Cycle

Combined Cycle is a 124 MW other request withdrawn in the ISO-NE interconnection queue, in Orleans County, Vermont.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2005 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
133
Grid region
ISO-NE (New England)
Connection point (POI)
Newport 115 kV Substation
Location
Orleans County, Vermont
Technology
Oil: 124 MW
Total requested
124 MW
Service type
Other
Queue status
Withdrawn
Entered queue
1 August 2005
Proposed online date
January 2010

Location

Marker shows the centre of Orleans County; the queue data does not give exact sites.

Power plants in Vermont Β· Transmission lines in Vermont

Other requests in Orleans County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem