United States βΊ Grid βΊ Interconnection queues βΊ Vermont
ONSHORE WIND Β· ISO-NEWind
Wind is a 60.0 MW onshore wind request withdrawn in the ISO-NE interconnection queue, in Caledonia County, Vermont.
Queue statusWithdrawn / abandoned
- PlanningQueued Jan 2012 (completed)
- Withdrawn / abandonedMay 2014 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 385
- Grid region
- ISO-NE (New England)
- Connection point (POI)
- VELCO 115 kV Lyndonville substation
- Location
- Caledonia County, Vermont
- Technology
- Wind: 60.0 MW
- Total requested
- 60.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- System Impact Study
- Queue status
- Withdrawn
- Entered queue
- 6 January 2012
- Proposed online date
- December 2015
- Withdrawn
- May 2014
Location
Marker shows the centre of Caledonia County; the queue data does not give exact sites.
Other requests in Caledonia County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem