United States βΊ Grid βΊ Interconnection queues βΊ Vermont
ONSHORE WIND Β· ISO-NEWind Repower
Wind Repower is a 35.2 MW onshore wind request withdrawn in the ISO-NE interconnection queue, in Caledonia County, Vermont.
Queue statusWithdrawn / abandoned
- PlanningQueued Dec 2023 (completed)
- Withdrawn / abandonedOct 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 1464
- Grid region
- ISO-NE (New England)
- Connection point (POI)
- VELCO, 115kV, Sheffield Substation 44.663509, -72.123160
- Location
- Caledonia County, Vermont
- Technology
- Wind: 35.2 MW
- Total requested
- 35.2 MW
- Service type
- Network resource (NRIS)
- Queue status
- Withdrawn
- Entered queue
- 5 December 2023
- Proposed online date
- December 2026
- Withdrawn
- October 2025
Location
Marker shows the centre of Caledonia County; the queue data does not give exact sites.
Other requests in Caledonia County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem