πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Vermont

OTHER Β· ISO-NE

Biomass

Biomass is a 30.0 MW other request withdrawn in the ISO-NE interconnection queue, in Windsor County, Vermont.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2008 (completed)
  2. Withdrawn / abandonedFeb 2009 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
279
Grid region
ISO-NE (New England)
Connection point (POI)
CVPS 46kV circuit in Springfield area
Location
Windsor County, Vermont
Technology
Other: 30.0 MW
Total requested
30.0 MW
Service type
Other
Queue status
Withdrawn
Entered queue
30 September 2008
Proposed online date
May 2011
Withdrawn
February 2009

Location

Marker shows the centre of Windsor County; the queue data does not give exact sites.

Power plants in Vermont Β· Transmission lines in Vermont

Other requests in Windsor County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem