United States › Grid › Interconnection queues › Vermont
SOLAR · ISO-NECoolidge Solar
Coolidge Solar is a 19.9 MW solar request built and operating in the ISO-NE interconnection queue, in Windsor County, Vermont.
Request details
- Queue ID
- 565
- Grid region
- ISO-NE (New England)
- Connection point (POI)
- 115 kV Coolidge Substation
- Location
- Windsor County, Vermont
- Technology
- Solar: 19.9 MW
- Total requested
- 19.9 MW
- Service type
- Network resource (NRIS)
- Study phase
- Executed
- Queue status
- Operational
- Entered queue
- 8 September 2015
- Agreement signed
- 28 February 2018
- Proposed online date
- December 2018
Location
Marker shows the centre of Windsor County; the queue data does not give exact sites.
Other requests in Windsor County
- Battery StorageBattery storage · 19.3 MW · in study
- Battery StorageBattery storage · 180 MW · withdrawn
- Battery StorageBattery storage · 115 MW · withdrawn
- Battery StorageBattery storage · 105 MW · withdrawn
- BiomassOther · 37.0 MW · withdrawn
- BiomassOther · 30.0 MW · withdrawn
- BiomassOther · 30.0 MW · withdrawn
- BiomassOther · 27.5 MW · withdrawn
- BiomassOther · 27.5 MW · withdrawn
- solarSolar · 20.0 MW · withdrawn
- SolarSolar · 19.9 MW · withdrawn
- SolarSolar · 19.9 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem