United States βΊ Grid βΊ Interconnection queues βΊ Vermont
OTHER Β· ISO-NEBiomass
Biomass is a 37.0 MW other request withdrawn in the ISO-NE interconnection queue, in Windsor County, Vermont.
Queue statusWithdrawn / abandoned
- PlanningQueued May 2013 (completed)
- Withdrawn / abandonedFeb 2014 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 418
- Grid region
- ISO-NE (New England)
- Connection point (POI)
- GMP L97 Line
- Location
- Windsor County, Vermont
- Technology
- Oil: 37.0 MW Β· Other
- Total requested
- 37.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- System Impact Study
- Queue status
- Withdrawn
- Entered queue
- 1 May 2013
- Proposed online date
- August 2015
- Withdrawn
- February 2014
Location
Marker shows the centre of Windsor County; the queue data does not give exact sites.
Other requests in Windsor County
- Battery StorageBattery storage Β· 19.3 MW Β· in study
- Coolidge SolarSolar Β· 19.9 MW Β· built
- Battery StorageBattery storage Β· 180 MW Β· withdrawn
- Battery StorageBattery storage Β· 115 MW Β· withdrawn
- Battery StorageBattery storage Β· 105 MW Β· withdrawn
- BiomassOther Β· 30.0 MW Β· withdrawn
- BiomassOther Β· 30.0 MW Β· withdrawn
- BiomassOther Β· 27.5 MW Β· withdrawn
- BiomassOther Β· 27.5 MW Β· withdrawn
- solarSolar Β· 20.0 MW Β· withdrawn
- SolarSolar Β· 19.9 MW Β· withdrawn
- SolarSolar Β· 19.9 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem