United States βΊ Grid βΊ Interconnection queues βΊ Vermont
SOLAR Β· ISO-NESolar
Solar is a 19.9 MW solar request withdrawn in the ISO-NE interconnection queue, in Windsor County, Vermont.
Queue statusWithdrawn / abandoned
- PlanningQueued Jul 2016 (completed)
- Withdrawn / abandonedJul 2016 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 616
- Grid region
- ISO-NE (New England)
- Connection point (POI)
- 115 kV Cooolidge Substation
- Location
- Windsor County, Vermont
- Technology
- Solar: 19.9 MW
- Total requested
- 19.9 MW
- Service type
- Network resource (NRIS)
- Queue status
- Withdrawn
- Entered queue
- 1 July 2016
- Proposed online date
- July 2017
- Withdrawn
- July 2016
Location
Marker shows the centre of Windsor County; the queue data does not give exact sites.
Other requests in Windsor County
- Battery StorageBattery storage Β· 19.3 MW Β· in study
- Coolidge SolarSolar Β· 19.9 MW Β· built
- Battery StorageBattery storage Β· 180 MW Β· withdrawn
- Battery StorageBattery storage Β· 115 MW Β· withdrawn
- Battery StorageBattery storage Β· 105 MW Β· withdrawn
- BiomassOther Β· 37.0 MW Β· withdrawn
- BiomassOther Β· 30.0 MW Β· withdrawn
- BiomassOther Β· 30.0 MW Β· withdrawn
- BiomassOther Β· 27.5 MW Β· withdrawn
- BiomassOther Β· 27.5 MW Β· withdrawn
- solarSolar Β· 20.0 MW Β· withdrawn
- SolarSolar Β· 19.9 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem